Secrets of Successful Project Management
|
|
Managing
software projects is difficult under the best circumstances. Unfortunately, many
new project managers receive virtually no job training. Here are 20 tips for
success.
by Karl Wiegers (Karl Wiegers is the principal consultant at Process
Impact and a contributing editor to Software Development)
- Define project success
criteria.
At the beginning of the project, make sure the stakeholders share a common
understanding of how they will determine whether this project is successful.
Too often, meeting a predetermined schedule is the only apparent success
factor, but there are certainly others. Some examples are increasing market
share, reaching a specified sales volume or revenue, achieving specific
customer satisfaction measures, retiring a high-maintenance legacy system,
and achieving a particular transaction processing volume and correctness.
- Identify project drivers,
constraints, and degrees of freedom.
Every project needs to balance its functionality, staffing, budget,
schedule, and quality objectives. Define each of these five project
dimensions as either a constraint within which you must operate, a driver
aligned with project success, or a degree of freedom that you can adjust
within some stated bounds to succeed. For more details about this, see
Chapter 2 of my book Creating a Software Engineering Culture (Dorset
House, 1996).
- Define product release
criteria.
Early in the project, decide what criteria will determine whether or not the
product is ready for release. You might base release criteria on the number
of high-priority defects still open, performance measurements, specific
functionality being fully operational, or other indicators that the project
has met its goals. Whatever criteria you choose should be realistic,
measurable, documented, and aligned with what “quality” means to your
customers.
- Negotiate commitments.
Despite pressure to promise the impossible, never make a commitment you know
you can’t keep. Engage in good-faith negotiations with customers and
managers about what is realistically achievable. Any data you have from
previous projects will help you make persuasive arguments, although there is
no real defense against unreasonable people.
- Write a plan.
Some people believe the time spent writing a plan could be better spent
writing code, but I don’t agree. The hard part isn’t writing the plan.
The hard part is actually doing the planning—thinking, negotiating,
balancing, talking, asking, and listening. The time you spend analyzing what
it will take to solve the problem will reduce the number of surprises you
have to cope with later in the project.
- Decompose tasks to inch-pebble
granularity.
Inch-pebbles are miniature milestones. Breaking large tasks into multiple
small tasks helps you estimate them more accurately, reveals work activities
you might not have thought of otherwise, and permits more accurate,
fine-grained status tracking.
- Develop planning work sheets
for common large tasks.
If your team frequently undertakes certain common tasks, such as
implementing a new object class, develop activity checklists and planning
worksheets for these tasks. Each checklist should include all of the steps
the large task might need. These checklists and worksheets will help each
team member identify and estimate the effort associated with each instance
of the large task he or she must tackle.
- Plan to do rework after a
quality control activity.
Almost all quality control activities, such as testing and technical
reviews, find defects or other improvement opportunities. Your project
schedule or work breakdown structure should include rework as a discrete
task after every quality control activity. If you don’t actually have to
do any rework, great; you’re ahead of schedule on that task. But don’t
count on it.
- Plan time for process
improvement.
Your team members are already swamped with their current project
assignments, but if you want the group to rise to a higher plane of software
engineering capability, you’ll have to invest some time in process
improvement. Set aside some time from your project schedule, because
software project activities should include making process changes that will
help your next project be even more successful. Don’t allocate 100% of
your team members’ available time to project tasks and then wonder why
they don’t make any progress on the improvement initiatives.
- Manage project risks.
If you don’t identify and control risks, they will control you. Spend some
time during project planning to brainstorm possible risk factors, evaluate
their potential threat, and decide how you can mitigate or prevent them. For
a concise tutorial on software risk management, see my article “Know Your
Enemy: Software Risk Management” (Oct. 1998).
- Estimate based on effort, not
calendar time.
People generally provide estimates in units of calendar time, but I prefer
to estimate the amount of effort (in labor hours) associated with a task,
then translate the effort into a calendar-time estimate. This translation is
based on estimates of how many effective hours I can spend on project tasks
per day, any interruptions or emergency fix requests I might get, meetings,
and all the other places into which time disappears.
- Don’t schedule people for
more than 80% of their time.
Tracking the average weekly hours that your team members actually spend
working on their project assignments is a real eye-opener. The
task-switching overhead associated with the many activities we are all asked
to do reduces our effectiveness significantly. Don’t assume that just
because someone spends 10 hours per week on a particular activity, he or she
can do four of them at once; you’ll be lucky if he or she can handle
three.
- Build training time into the
schedule.
Determine how much time your team members typically spend on training
activities annually, and subtract that from the time available for them to
be assigned to project tasks. You probably already subtract out average
values for vacation time, sick time, and other assignments; treat training
time the same way.
- Record estimates and how you
derived them.
When you prepare estimates for your work, write them down and document how
you arrived at each one. Understanding the assumptions and approaches used
to create an estimate will make them easier to defend and adjust when
necessary, and it will help you improve your estimation process.
- Record estimates and use
estimation tools.
Many commercial tools are available to help you estimate entire projects.
With their large databases of actual project experience, these tools can
give you a spectrum of possible schedule and staff allocation options.
They’ll also help you stay out of the “impossible region,”
combinations of product size, team size, and schedule where no known project
has been successful. A good tool to try is Estimate Pro from the Software
Productivity Centre (www.spc.ca).
- Respect the learning curve.
If you’re trying new processes, tools, or technologies for the first time
on this project, recognize that you will pay a price in terms of a
short-term productivity loss. Don’t expect to get the fabulous benefits of
new software engineering approaches on the first try, and build extra time
into the schedule to account for the inevitable learning curve.
- Plan contingency buffers.
Things never go precisely as you plan on a project, so your budget and
schedule should include some contingency buffers at the end of major phases
to accommodate the unforeseen. Unfortunately, your manager or customer may
view these buffers as padding, rather than the sensible acknowledgement of
reality that they are. Point to unpleasant surprises on previous projects as
a rationale for your foresight.
- Record actuals and estimates.
If you don’t record the actual effort or time spent on each task and
compare them to your estimates, you’ll never improve your estimating
approach. Your estimates will forever remain guesses.
- Count tasks as complete only
when they’re 100% complete.
One benefit of using inch-pebbles for task planning is that you can classify
each small task as either done or not done, which is more realistic than
trying to estimate what percent of a large task is complete at any time.
Don’t let people “round up” their task completion status; use explicit
criteria to tell whether a step truly is completed.
- Track project status openly
and honestly.
Create a climate in which team members feel safe reporting project status
accurately. Strive to run the project from a foundation of accurate,
data-based facts, rather than from the misleading optimism that sometimes
arises from fear of reporting bad news. Use project status information to
take corrective actions when necessary and to celebrate when you can.
These tips won’t guarantee success, but they will
help you get a solid handle on your project and ensure that you’re doing all
you can to make it succeed in a crazy world.